Second Allocation
Contract Reporting
Program Administrator
Awarded May 6, 2014—RFP for CDBG-DR 2nd Allocation Grant Admin. Services and Project Delivery
Agreement Between the City and CDM Smith for CDBG-DR Management Services for 2nd Allocation
- Amendment 1 - Agreement Between the City and CDM Smith for 2nd Allocation
- Amendment 2 - Agreement between City of Minot and Program Administration
- Amendment 3 - Agreement between City of Minot and Program Administration
- Amendment 4 - Agreement between City of Minot and Program Administration
- Amendment 5 - Agreement between City of Minot and Program Administration
- Amendment 6 - Agreement between City of Minot and Program Administration
- Amendment 7 - Agreement between City of Minot and Program Administration
- Amendment 8 - Agreement between City of Minot and Program Administration
- Amendment 9 - Agreement between City of Minot and Program Administration
Housing
Agreement Between City and Dig It Up – Structure Demolition and Site Restoration (04/07/15)
Awarded December 7, 2015, RFP for Eminent Domain Legal Services
Agreement between the City and Swanson and Warcup for Eminent Domain Legal Services
- 2018 Contract Extension for Agreement between the City of Minot and Swanson & Warcup for Eminent Domain Legal Services
- 2019 Contract Extension for Agreement between the City of Minot and Swanson & Warcup for Eminent Domain Legal Services
Awarded May 2, 2016. RFB for Structural Demo and Restoration
- Change Order 1 - Berger Enterprises Round 4 Demolition
- Change Order 2 - Berger Enterprises Round 4 Demolition 11-6-2018
Agreement Between City and Dig It Up – Structure Demolition and Site Restoration (12/11/17)
Infrastructure
Awarded September 2, 2014 – RFQ Engineering Services for Street Rehab in Flood Inundated Areas – Project 3873 & 3873.1
Ackerman-Estvold Agreement for Engineering for Flooded Streets
- Amendment #1 – Agreement for Engineering for Flooded Streets
- Amendment #2 – Agreement for Engineering for Flooded Streets
Agreement City and Wagner Constr. for 16th Ave, 46th St and 14th Ave SE Rebuild
- Change Order #1 16th & 14th Ave SE & 46th St. Rebuild Wagner
- Change Order #2 16th & 14th Ave SE & 46th St. Rebuild Wagner
- Change Order #3 16th & 14th Ave SE & 46th St. Rebuild Wagner
- Change Order #4 16th & 14th Ave SE & 46th St. Rebuild Wagner
- Change Order #5 16th & 14th Ave SE & 46th St. Rebuild Wagner
- Change Order #6 16th & 14th Ave SE & 46th St. Rebuild Wagner
Agreement between City and Bechtold Paving for Flooded Street Repair - Section 1
Agreement between City and Bechtold Paving for Flooded Street Repair - Section 2
- Change Order #1 for Section 1 Bechtold Paving
- Change Order #2 for Section 1 Bechtold Paving
- Change Order #3 for Section 1 Bechtold Paving
- Change Order #4 for Section 1 Bechtold Paving
- Change Order #1 for Section 2 Bechtold Paving
- Change Order #2 for Section 2 Bechtold Paving
- Change Order #3 for Section 2 Bechtold Paving
- Change Order #4 for Section 2 Bechtold Paving
- Change Order #5 for Section 2 Bechtold Paving
- Change Order #1 Street Improvements 55th Crossing
- C Change Order #2 Street Improvements 55th Crossing
Planning
RFQ Anne St Bridge Condition Assessment Project 4385
Agreement between City of Minot and EAPC – Anne St Bridge Condition Assessment Feb 11, 2019
Analysis of Impediments to Fair Housing Choice for Minot